Furnish the VIP-lodges began to "Rostov-Arena"

Construction readiness stadium is 76%

Furnish the VIP-boxes (skybox) began at the stadium "Rostov-Arena", is being built in the capital of the Don to the World Cup 2018 years.

According to information from official sources, completed reinforced concrete works. Almost completed the device monolithic structures, thermal insulation of external walls of the facade, podtribunnogo space.

Completed masonry walls and partitions, plastering works, installation of ventilation systems, sewerage and water supply.

There is base stacking ballast football field.

It installed more than 18 thousand square meters. meters polymeric roofing. A montage of elevators, windows, glass windows, window frames, as well as media facades system.

Construction readiness "Rostov-Arena" has reached 76%. The deadline for completion - December 25 2017 years.

Source: Arguments and Facts